自由浮动时间(Free Float)与总浮动时间(Total Float)的区别在于( )。选项A)自由浮动时间是总浮动时间中对结束日期没有影响的那部分,而总浮动时
自由浮动时间(Free Float)与总浮动时间(Total Float)的区别在于()。A.自由浮动时间是总浮动时间中对结束日期没有影响的那部分,而总浮动时间是自由浮动
Total float and free float are important concepts in schedule management. Total float is commonly referred to as float. Activities on a non-critical path will have a total float. When two activities converge, one of them will have a free float. This topic is important from a PMP exam point...
自由浮动时间(Free Float)与总浮动时间(Total Float)的区别在于()。A.自由浮动时间是总浮动时间中对结束日期没有影响的那部分,而总浮动时间是自由浮动时间的累计值B.自由浮动时间只影响今后活动的最早开始时间C.自由浮动时间常常指“时差”(Slack time),而总浮动
Total Float vs Free Float Total Float and Free Float are very different concepts. Although they are calculated for each activity, they serve entirely different purpose. Total Float is concerned with the project finish date whereas Free Float is concerned with the immediate predecessor(s) of an ac...
D.An activity's free float is calculated by subtracting its total float from the critical path's total float. 相关知识点: 试题来源: 解析 C [解析] 自由时差与总时差的区别是 A) 自由时差是不影响结束日期的总时差, 总时差是自由时差的总和。 B) 毫无区别, 作用一致。 C) 自由时差是一个进度活动...
Free Float vs. Total Float is a widely talked about topic in Project Management. Learn the key differences between these 2 project terminologies in this article.
total float n free float 文档格式: .pdf 文档大小: 1.04M 文档页数: 6页 顶/踩数: 0/0 收藏人数: 0 评论次数: 0 文档热度: 文档分类: 外语学习--英语学习 文档标签: totalfloatnfree total float n free float,total float n free float,total,float,n,free ...
2015-05-23上传 Total Float n Free Float 文档格式: .pdf 文档大小: 1.04M 文档页数: 6页 顶/踩数: 0/0 收藏人数: 0 评论次数: 0 文档热度: 文档分类: 待分类 文档标签: TotalFloatnFree Total Float n Free Float,Total Float n Free Float,Total,Float,n,Free ...
摘要: Float time is an important time parameter in the network planning. The article discusses the calculation of total floats and free floats, and analyses its function.关键词: Time—Scaled Network Diagram free float total float 年份: 2015 ...