The Interstate 45 Sanitary Sewer Rehabilitation project rehabilitated the existing 54-inch trunk line. The solution consisted of sliplining with 535 feet of 48-inch diameter Hobas Centrifugally Cast Fiberglass
1 involved sliplining 4,000 feet of 84-inch deteriorated concrete sanitary gravity sewer pipe with 72-inch fiberglass pipe.The project is in a growing suburban area east of Richmond, VA. It involved six horizontal curve sections and three crossings of a major interstate highway. Although there...
Many cities and municipal utility districts are having to repair sanitary and storm sewers. A leaking sewer will typically allow sand, clays, silts and other materials to seep into the sewer. The subsequent flow of water through the sewer carries such materials away so that with time voids are...
The city of San Jose, California, recently completed phase II of the Senter-Monterey Sanitary Sewer Rehabilitation project. The project involved sliplining... KL Salvail,D Gellings 被引量: 0发表: 1997年 Structural Design Methodology for Spray Applied Pipe Liners in Gravity Storm Water Conveyance...
The Interstate 45 Sanitary Sewer Rehabilitation project rehabilitated the existing 54-inch trunk line. The solution consisted of sliplining with 535 feet of 48-inch diameter Hobas Centrifugally Cast Fiberglass Reinforced Polymer Mortar (CCFRPM) pipe. As the main trunk line flowing into the only ...
The article focuses on the complex sliplining problem encountered at the Four-mile Creek Trunk Sewer Rehabilitation Project Contract No. 1 in Henrico County, Virginia. It was stated that the $8.9 million sewer project involved a 4,000 feet slipline of a 84-inch deteriorated concrete sanitary ...