Both the planning in MRP Live on HANA and classic MRP has to be completed for one low-level code before the system commences the planning of the next low-level code (1). That is, during the planning process, the system divides the materials into groups: Materials that can be planned ...
🚀在SAP的MRP软件中,确保物料可用性是其主要功能。它通过库存监控和自动创建采购和生产建议,优化服务水平和降低成本。📊💥随着技术的进步,SAP MRP不断进化。HANA和AMDP技术的引入,使得基于SAP Classical MRP的Performance Critical操作得以重构,从而诞生了SAP MRP Live。🚀🎉使用MRP Live,企业可以享受经过HANA优...
SAP MRP 自身也在不断进化。HANA 和 AMDP 技术问世后,基于 SAP Classical MRP,那些 Performance Critical 的操作,用 ADMP 重构,由此诞生了一个新的应用:SAP MRP Live. 关于AMDP 技术,可以参考我之前的文章: 。 使用MRP Live,我们可以受益于经过 HANA 优化后的性能,从而能够以更短的周期执行 MRP,比如每天能够执...
MRP live (transaction MD01N) is designed to perform MRP for a large set of materials in one or even multiple locations with fast runtime. The improvement in performance in MRP live on HANA compared to classic MRP depends on the following: MRP features used Number of materials to be planned...
5.ECC和S/4 HANA MRP运行上的差异 Ø5.1 MRP经典模式 vs MRP LIVE Ø5.2. S4系统如何决定是选择MRP LIVE还是经典模式 Ø5.3 MRP处理代码和计划模式上的差异 Ø5.4 MRP计划文件上的差异 Ø5.5 其他差异及MRP运行上差异汇总 6.PP和MM模块集成点相关功能上的差异 ...
MRP List是 classic MRP的特征。它给出了最后一次MRP运行时的需求和供应情况。MRP Live实时提供库存需求清单。可以快速确定物料问题。 S / 4 HANA强制要求生产版本 在classic ECC系统中 - 逻辑正在考虑BOM的有效性,而在S / 4系统中,它正在寻找具有有效生产版本的BOM。因此,必须在S / 4 HANA中维护生产版本(即使...
一、物料主数据的MRP区域设置 SAP ECC系统中想要指定不影响MRP运算的库存地点,是针对库存地点设置MRP标识...
Solved: Hi, I am trying to run MRP live (MD01N), 2 different users, same plant but different range of materials, example: Plant: PL01 Range 1 materials : ABC100 to
Solved: Dear All, S/4Hana : 1709 1)FG which has two components attached in BOM. 2)All three materials are getting planned in MD02 ( After MRP run, Can see plan orders
至少有9年以上的SAP PP经验,至少有5个端到端的实施项目,从项目准备到S4HANA的上线。 - 至少有3到5个端到端实施项目的经验,设计和配置PP的流程- MTS, MTO, ETO, ATO, MRP, Production Execution, LTP,SOP 和 Variant Configuration。 - 还应了解这些流程如何整合财务、成本计算、库存管理、采购、销售和仓库管...