The underlying principles, the drafting style, and the option structure format of Engineering and Construction Contract4 (ECC) remain as in previous editio... B Eggleston - The NEC4 Engineering and Construction Contract 被引量: 0发表: 2019年 Early Warning of NEC3 ECC, A Solution for Dutch De...
It contains all core clauses and secondary option clauses, together with the schedules of cost components and forms for contract data. Early Contractor Involvement (ECI) NEC has developed an additional clause to be used with the NEC3 Engineering and Construction Contract (ECC) ...
So far this tells us very little; the NEC3 ECC Guidance Notes offers some help by providing the following explanation for Main Option A: An activity schedule is a list of activities prepared by the Contractor which he expects to carry out in Providing the Works. When it has been priced by...