cost performance index 成本绩效指数 performance index 演绩指数,性能指标,生产性能指数 cost performance 费用性能,单位成本率,成本效率,性能价格比,价格性能,价格性能比 cost index 费用指数 main performance index 主要性能指标 system performance index 系统性能指标 specific performance index 特性指数 qua...
A Cost Performance Index ( CPI) threshold value is expressed as a ratio. An issue is generated if the CPI falls beyond the threshold values. The Cost Performance Index is calculated as CPI = Earned Value Cost / Actual Cost . A value less than 1 indicates that actual costs have exceeded ...
150 The Cost Performance Index (CPI) measures: A. cost of work performed vs planned costs. B. work performed vs cost of work performed. C. work performed vs planned work. D. direct costs vs indirect costs. E. floating costs vs. sunk costs ...
成本绩效指数(Cost Performance Index CPI):成本效果的量度。是项目的已完成工作的实际成本和已完成工作的预算成本的比值。www.cnblogs.com|基于2个网页 例句 释义: 全部,成本绩效指数 更多例句筛选 1. A useful cost indicator is the Cost Performance Index (CPI) shown in Figure 6. Like the SPI, the CPI...
Cost performance index is used as a performance indicator. Lesson Quiz Course 9.3K views Definition and Formula of Cost Performance Index Cost performance index (CPI) is calculated using the following formula: CPI = (earned value) / (actual cost) Earned value is abbreviated as EV and...
挣值(Earned Value,EV)。EV是在既定的时间段内实际完工工作的预算成本。 实际成本(Actual Cost,AC)。AC是在既定的时间段内实际完成工作发生的实际总成本。 成本偏差(Cost Variance,CV)。CV等于EV减AC。计算公式为:CV=EV-AC 进度偏差(Schedule Variance,SV)。SV等于EV减PV。计算公式为:SV=EV-PV ...
CPI = EV/AC = BCWP/ACWP = (P0*Q1)/(P1*Q1)。 此指标的含义为:项目实际已完成作业量的实际成本和预算成本之间的相对差异值。它排除了项目实际作业量变动带来的影响,进而衡量项目成本控制工作的绩效状况,是项目成本绝对差异指标的相对数形式。该指标值大于1较好,反之就意味着项目成本管理存在问题。 复制 纠错...
If the value of CPI is greater than 1, the project is currently successful against the budget. The value of CPI equals zero tells that for $1 USD spent you get $1 USD of performance. Cost Performance Index (CPI) per Project is one of the most important KPIs in project management. Co...
The Cost Performance Index (CPI) measures: A.cost of work performed vs planned costs. B.work performed vs cost of work performed. C.work performed vs planned work. D.direct costs vs indirect costs. E.floating costs vs. sunk costs. ...
How do you calculate the schedule performance index? The schedule performance index equals the earned value divided by the planned value. Where earned value is equal to the budgeted cost of the steps completed, and planned value is the budgeted cost of the steps that should have been completed...