成本绩效指数(Cost Performance Index CPI):成本效果的量度。是项目的已完成工作的实际成本和已完成工作的预算成本的比值。www.cnblogs.com|基于2个网页 例句 释义: 全部,成本绩效指数 更多例句筛选 1. A useful cost indicator is the Cost Performance Index (CPI) shown in Figure 6. Like the SPI, the CPI...
成本绩效指数(CPI)是衡量项目管理中成本绩效的指标,公式为CPI=EV/AC或CPI=BCWP/ACWP。CPI<1.0表示实际成本超出
Cost Performance Index (CPI)is A. Ratio of Earned Value (EV) to Actual Cost (AC) B. Ratio of Earned Value (EV) to Budgeted Cost (BC) C. Ratio of Cost Variance (CV) to Actual Cost (AC) D. Ratio of Planned Value (PV) to Budgeted Cost (BC) ...
Cost Performance Index ( CPI) (ratio) A Cost Performance Index ( CPI) threshold value is expressed as a ratio. An issue is generated if the CPI falls beyond the threshold values. The Cost Performance Index is calculated as CPI = Earned Value Cost / Actual Cost . A value less than 1 ...
CPI 英文全称cost performance index 中文解释费用执行效果指数 缩写分类土木建筑, IVP静脉肾盂造影 KUB尿路平片 HIFU高能聚焦超声 TURP经尿道前列腺切除术 TURBt经尿道膀胱肿瘤切除术 Scr血肌酐 STDs性传播疾病 PCNL经皮肾镜取石 PSA前列腺特异抗原 ERPF有效肾血浆流量 ...
cost performance index CPI的意思 CPI 英文缩写CPI 英文全称cost performance index 中文解释费用执行效果指数 缩写分类土木建筑 缩写简介
The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project. A. cost variance B. planned cost C. schedule variance D. actual cost 相关知识点: 试题来源: ...
一个任务原计划3个人全职工作2周完成,而实际上只有2个人参与这个任务,到第二周末完成了任务的50%,则CPI= 75% 。 A.解析:p319,(Cost Performance Index)CPI(成本效能指标)=BCWP(已经完成工作的成本预算)/ACWP(到目前为止花了多少钱)*100%;此指标表示花钱的速度。B.此题,CPI=(3/2)/2*100%=0.75。C....
英文缩写 CPI 英文缩写CPI 英文全称cost performance index 中文解释费用执行效果指数 CPI意思,CPI的意思,CPI是什么意思?爱站小工具网缩写频道为您提供有关于CPI的解释和缩写,费用执行效果指数的英文缩写是什么
CPI = EV/AC = BCWP/ACWP = (P0*Q1)/(P1*Q1)。 此指标的含义为:项目实际已完成作业量的实际成本和预算成本之间的相对差异值。它排除了项目实际作业量变动带来的影响,进而衡量项目成本控制工作的绩效状况,是项目成本绝对差异指标的相对数形式。该指标值大于1较好,反之就意味着项目成本管理存在问题。 复制 纠错...