[解析] 你所在的建筑项目的CPI为1.3, SPI为0.85。下列哪项是潜在的原因 A) 关键资源长时间离开, 这是之前没有预料到的。 B) 建筑所需材料的成本增加了10%。 C) 你以前没考虑通货膨胀率。 D) 在水泥加工中有四天的等待时间, 这段时间内无法工作。
The installation project has a CPI of 1.03 and an SPI of 1.0. There are 14 team members and each team member had input into the final project management plan. The customer has accepted the three deliverable completed so far without complaint and the responsibility assignment matrix has not ...
We’ll share the formula for calculating the cost performance index in project management and even provide an example to better illustrate how it works. What Is the Cost Performance Index (CPI)? The cost performance index is a way to measure the financial performance of a project. It can ...
Cost Performance Index (CPI) = EV / AC (a CPI less than 1 indicates a cost overrun). Schedule Performance Index (SPI) = EV / PV (an SPI equal to or greater than 1 indicates the project is in a favorable condition). For example, the budgeted cost (planned value) for a project at...
SPI SplitParts Start Start1 Start10 Start2 Start3 Start4 Start5 Start6 Start7 Start8 Start9 StartDriver StartSlack StartText StartVariance Status StatusManagerName Stop Subproject SubProjectReadOnly Successors SuccessorTasks Summary SV SVPercent TaskDependencies TCPI TeamStatusPending Text1 Text10 Text...
For this example, we’ll use the first Estimate to Complete formula variation. As a reminder, here’s what that equation looks like: EAC = BAC / CPI In this scenario, the Budget at Completion (BAC) is $50,000 and the current Cost Performance Index (CPI) is equal to 0.8. Therefore,...
项目经理确定项目的进度绩效指数(SPI)为1.2,成本绩效指数(CPI)为0.8.项目目前的状态是什么?A project manager determines that the a project's schedule performanceindex(SPI)is 1.2,and its cost performance index(CPI)is 0.8.What is the project a current status?
A project has an SPI<1 and a CPI>1. The project manager should take which of the following corrective actions? A. Crashing B. Fast tracking C. Resource leveling D. Monte Carlo ysis 如何将EXCEL生成题库手机刷题 如何制作自己的在线小题库 >...
Cpi TaskProperties.CreationDate TaskProperties.CummulativePercentComplete TaskProperties.CumulativeActualWork TaskProperties.CumulativeCost TaskProperties.CumulativeWork TaskProperties.CV TaskProperties.Cvp TaskProperties.Date1 TaskProperties.Date10 TaskProperties.Date2 TaskProperties.Date3 Tas...
CPI = EV ÷ AC schedule_performance_index (SPI) It is based on the formula: SPI = EV ÷ PV estimate_at_completion (EAC) It is based on the formula: EAC = AC + (BAC - EV) ÷ CPI = AC + ETC estimate_to_completion (ETC) ...